Permit no. : 23310
Location : الدور الأول فاصل ١
Issue Date : أكتوبر 9, 2024
Issue Time : 12:10
Status : Valid
A.Description of Work and affected utilities
استكمال أعمال تشطيب سيليكون
B. Work requiest details
1. Permit type
Others
2. Application by Department / Contractor
Contractor: شركة آفاق
Name: صلاح عبد الراضي
ID#: ٢٨٧٠٢٠٦٢٧٠٠٥٧٢
Job:
Contractor: شركة آفاق
Name: شعبان أحمد فهمي
ID#: ٢٩٠١٣٠٥٢٧٠١٥٧٦
Job:
3. Equipment used
Light Tools
C. Permit duration
October 9, 2024
Permit Expiration Date : October 9, 2024
Note : The permit is considered automatically canceled in the event of the expiry of the permit date period or a violation of one of the mentioned occupational safety and health requirements
D. Hazards Identification
Dangerous Chemicals
E. Obligatory Safety Recommendation
Fire Extinguisher is available and accessible
Isolation signage & PPE used appropriately
The place is free of flammable materials
Do not use any equipment not mentioned in the work permit without consulting the safety official
Electrical connections are free of cutting or welding
F. Personal protective equipments required
Chemical gloves
Safety shoes
G. Approvals
Maintanance Manager :
Approved
H. Permit Follow up
Notification sent to
ehab.rezk@aljoud-ngo.com
mohamed.salah@aljoud-ngo.com